Project Objectives & Components
The development objective of the Project is to reduce the cost and increase the availability of ICT services needed to support social and economic
development in the Recipient’s territory.
Has the Project Development Objective been changed since Board Approval of the Project Objective?
No
Components
Component 1A Palau-Yap-Guam Cable System:(Cost $22.50 M)
Component 1B Chuuk-Pohnpei Cable System:(Cost $18.50 M)
Component 1C Kosrae Connectivity:(Cost $3.50 M)
Component 2 Technical Assistance:(Cost $2.25 M)
Component 3 Project Management:(Cost $0.75 M)